Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P52100053442

Mokate Kalanidhi · Kothrud, Pune · Sharada Alliance Promoters & Builders

Promised for 31 Dec 2028, extended to 30 Apr 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2028 to 30 Apr 2029.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate1 Nov 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100053442

Is Mokate Kalanidhi delayed?

Its completion moved from 31 Dec 2028 to 30 Apr 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100053442. The completion date moved from 31 Dec 2028 to 30 Apr 2029.

Who is the promoter?

MahaRERA records Sharada Alliance Promoters & Builders as the promoter of P52100053442.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100053442.

Answers are generated from the record.

Data through23 Nov 2026, 01:51SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology