Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Completed

P52100051176

Sai Pearl · Pimpale Saudagar, Pune · Ssd Promoters And Builders

Promised for 31 Dec 2025; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 22

Commencement certificate28 Feb 2023View
Form B28 Feb 2023View
Form 128 Feb 2023View
Other28 Feb 2023View
Other28 Feb 2023View
Title report24 May 2023View
Registration certificate1 Jun 2023View
Form 118 Aug 2023View
Show all 22 documents
Other18 Aug 2023View
Form 217 Oct 2023View
Allotment letter20 Mar 2024View
Form 116 Apr 2024View
Form 216 Apr 2024View
Form 420 Jul 2024View
OtherView
OtherView
Layout planView
Building planView
Building planView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100051176

Is Sai Pearl delayed?

MahaRERA reports it completed. Its promised completion date was 31 Dec 2025.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100051176.

Who is the promoter?

MahaRERA records Ssd Promoters And Builders as the promoter of P52100051176.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100051176.

Answers are generated from the record.

Data through9 Nov 2026, 02:27SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology