RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52100050769

Nestoria Baner · Baner, Pune · Supreme Palatial Developers Llp

Promised for 31 Dec 2023 — that date has passed and MahaRERA does not mark the project complete.

2 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2023, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate3 May 2023View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100050769

Is Nestoria Baner delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100050769.

Who is the promoter?

MahaRERA records Supreme Palatial Developers Llp as the promoter of P52100050769.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100050769.