RegisteredMahaRERA status: Certificate Signed

P52100049545

Escape City Ph 2 · Dhamane, Pune · Gajendra Patil , Pramod Patil , Vinod Patil

Promised for 31 Dec 2027 and not extended so far.

1 year and 1 month to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate15 Feb 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100049545

Is Escape City Ph 2 delayed?

Not so far. MahaRERA records a promised completion of 31 Dec 2027, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100049545.

Who is the promoter?

MahaRERA records Gajendra Patil , Pramod Patil , Vinod Patil as the promoter of P52100049545.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100049545.

Answers are generated from the record.

Data through16 Nov 2026, 02:08SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology