RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100048711
Mudaliars Heritage · Pune (M Corp.), Pune · Citi Developers
Promised for 31 Jul 2025 — that date has passed and MahaRERA does not mark the project complete.
1 year and 4 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Risk: The latest completion date on record, 31 Jul 2025, has passed.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100048711
Is Mudaliars Heritage delayed?
Yes. MahaRERA records a promised completion of 31 Jul 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 0 extension certificates for P52100048711.
Who is the promoter?
MahaRERA records Citi Developers as the promoter of P52100048711.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100048711.
Answers are generated from the record.