Completed

P52100035155

Mokate Heritage · Kothrud, Pune · Mokate Constructions

Promised for 31 Dec 2024; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 13

Title report27 Apr 2022View
Form B27 Apr 2022View
Other2 May 2022View
Registration certificate10 May 2022View
Form 215 Mar 2023View
Commencement certificate4 Dec 2023View
Occupancy / completion certificate20 Feb 2024View
Other20 Feb 2024View
Show all 13 documents
OtherView
Building planView
Allotment letterView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100035155

Is Mokate Heritage delayed?

MahaRERA reports it completed. Its promised completion date was 31 Dec 2024.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100035155.

Who is the promoter?

MahaRERA records Mokate Constructions as the promoter of P52100035155.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100035155.