RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52100034484

Ananya Residency · Baramati Rural, Pune · Rajan Dhananjay Kolekar

Promised for 31 Mar 2025 — that date has passed and MahaRERA does not mark the project complete.

1 year and 8 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Mar 2025, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate11 Apr 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100034484

Is Ananya Residency delayed?

Yes. MahaRERA records a promised completion of 31 Mar 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100034484.

Who is the promoter?

MahaRERA records Rajan Dhananjay Kolekar as the promoter of P52100034484.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100034484.

Answers are generated from the record.

Data through9 Nov 2026, 02:53SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology