Completed

P52100034465

Heritage 28 · Baner, Pune · Kalyani Buildcon

Promised for 31 Dec 2025; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 11

Title report6 Apr 2022View
Form B6 Apr 2022View
Registration certificate11 Apr 2022View
Building plan29 Sep 2022View
Allotment letter17 Feb 2024View
Form 410 Jan 2025View
OtherView
Layout planView
Show all 11 documents
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100034465

Is Heritage 28 delayed?

MahaRERA reports it completed. Its promised completion date was 31 Dec 2025.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100034465.

Who is the promoter?

MahaRERA records Kalyani Buildcon as the promoter of P52100034465.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100034465.