Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100030155

61 Ideal · Kothrud, Pune · Samarth Builders

Promised for 1 Dec 2023, extended once to 30 Nov 2024 — and that date has passed without the project marked complete on MahaRERA.

2 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 1 Dec 2023 to 30 Nov 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Nov 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate31 Jul 2021View
Extension certificate22 Nov 2023View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100030155

Is 61 Ideal delayed?

Yes. MahaRERA records a promised completion of 1 Dec 2023, revised to 30 Nov 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100030155. The completion date moved from 1 Dec 2023 to 30 Nov 2024.

Who is the promoter?

MahaRERA records Samarth Builders as the promoter of P52100030155.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100030155.

Answers are generated from the record.

Data through3 Nov 2026, 02:03SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology