Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredMahaRERA status: Certificate Signed

P52100029777

Bappa Towers · Man, Pune · Pradeep Manohar Kodnani

Promised for 31 Dec 2026 and not extended so far.

1 month to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate29 Jun 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100029777

Is Bappa Towers delayed?

Not so far. MahaRERA records a promised completion of 31 Dec 2026, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100029777.

Who is the promoter?

MahaRERA records Pradeep Manohar Kodnani as the promoter of P52100029777.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100029777.

Answers are generated from the record.

Data through16 Nov 2026, 02:00SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology