Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered1 extensionMahaRERA status: Certificate Signed

P52100029449

Shaneshwar Samruddhi · Kalewadi Darekarwadi, Pune · Prithvi Construction

Promised for 15 Mar 2025, extended once to 30 Dec 2030, which is still ahead.

The revised date is 5 years and 9 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 15 Mar 2025 to 30 Dec 2030 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate29 May 2021View
Extension certificate11 May 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100029449

Is Shaneshwar Samruddhi delayed?

Its completion moved from 15 Mar 2025 to 30 Dec 2030; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100029449. The completion date moved from 15 Mar 2025 to 30 Dec 2030.

Who is the promoter?

MahaRERA records Prithvi Construction as the promoter of P52100029449.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100029449.

Answers are generated from the record.

Data through9 Nov 2026, 02:13SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology