RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100029164

Sai Sneh · Hadapsar, Pune · Nilesh Dilip Kale

Promised for 30 Apr 2023, extended once to 31 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

3 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Apr 2023 to 31 Dec 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate10 Oct 2023View
Extension certificate10 Oct 2023View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100029164

Is Sai Sneh delayed?

Yes. MahaRERA records a promised completion of 30 Apr 2023, revised to 31 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100029164. The completion date moved from 30 Apr 2023 to 31 Dec 2024.

Who is the promoter?

MahaRERA records Nilesh Dilip Kale as the promoter of P52100029164.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100029164.

Answers are generated from the record.

Data through9 Nov 2026, 02:13SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology