Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100028966
Sun Crest · Dhayari (Part), Pune · Jindal Mittal Infrastructure
Promised for 31 Mar 2024, extended once to 30 Sep 2025 — and that date has passed without the project marked complete on MahaRERA.
2 years and 8 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Mar 2024 to 30 Sep 2025 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Sep 2025, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 3
Orders 0
No MahaRERA order or list names this number.
Questions about P52100028966
Is Sun Crest delayed?
Yes. MahaRERA records a promised completion of 31 Mar 2024, revised to 30 Sep 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100028966. The completion date moved from 31 Mar 2024 to 30 Sep 2025.
Who is the promoter?
MahaRERA records Jindal Mittal Infrastructure as the promoter of P52100028966.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100028966.
Answers are generated from the record.