Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100027737

Rajmudra Phase 1 and 2 · Ale, Pune · Rajmudra Developers

Promised for 28 Nov 2022, extended once to 28 May 2024 — and that date has passed without the project marked complete on MahaRERA.

4 years past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 28 Nov 2022 to 28 May 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 28 May 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate3 Jan 2021View
Extension certificate8 Sep 2021View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100027737

Is Rajmudra Phase 1 and 2 delayed?

Yes. MahaRERA records a promised completion of 28 Nov 2022, revised to 28 May 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100027737. The completion date moved from 28 Nov 2022 to 28 May 2024.

Who is the promoter?

MahaRERA records Rajmudra Developers as the promoter of P52100027737.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100027737.

Answers are generated from the record.