RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100027356
34 Rupesh · Kothrud, Pune · Sham Prabhakar Deshpande
Promised for 31 Dec 2022, extended once to 31 Mar 2023 — and that date has passed without the project marked complete on MahaRERA.
3 years and 11 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2022 to 31 Mar 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Mar 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 3
Orders 0
No MahaRERA order or list names this number.
Questions about P52100027356
Is 34 Rupesh delayed?
Yes. MahaRERA records a promised completion of 31 Dec 2022, revised to 31 Mar 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100027356. The completion date moved from 31 Dec 2022 to 31 Mar 2023.
Who is the promoter?
MahaRERA records Sham Prabhakar Deshpande as the promoter of P52100027356.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100027356.
Answers are generated from the record.