Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered1 extensionMahaRERA status: Certificate Signed

P52100026757

Vaishnavi Arcade Phase 2 · Ambegaon Bk, Pune · Trimurti Developers

Promised for 31 Dec 2028, extended once to 30 Apr 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2028 to 30 Apr 2029 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Extension certificate12 Aug 2026View
Registration certificate14 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100026757

Is Vaishnavi Arcade Phase 2 delayed?

Its completion moved from 31 Dec 2028 to 30 Apr 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100026757. The completion date moved from 31 Dec 2028 to 30 Apr 2029.

Who is the promoter?

MahaRERA records Trimurti Developers as the promoter of P52100026757.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100026757.

Answers are generated from the record.

Data through9 Nov 2026, 02:12SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology