P52100026099

Emerald Bay · Mundhawa, Pune · Pune Projects Llp

Promised for 30 Jun 2028, extended once to 31 Dec 2029, which is still ahead.

The revised date is 1 year and 6 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2028 to 31 Dec 2029 (1 extension certificate on record).
  • Caution: 1 other MahaRERA order names this registration.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate8 Sep 2021View
Extension certificate6 Aug 2024View

Orders 1

Regulatory order

Regulatory order: PROJECT NAME:EMERALD BAY BUILDING 13 (Regulatory Case No. 270 OF 2024) dated 31 July 2024.

31 Jul 2024 · matched by RERA number

View order →

Questions about P52100026099

Is Emerald Bay delayed?

Its completion moved from 30 Jun 2028 to 31 Dec 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100026099. The completion date moved from 30 Jun 2028 to 31 Dec 2029.

Who is the promoter?

MahaRERA records Pune Projects Llp as the promoter of P52100026099.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P52100026099.

Answers are generated from the record.

Data through25 Oct 2026, 02:42SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology