Pune Projects Llp
Company or firm · 2 projects · 9 MahaRERA registrations
Projects29 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 4 past their proposed date, not extended
Median delay+18 movs RERA proposed date · 5 extended
Regulatory cases6MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Emerald BayP52100026016 | Mundhawa | 2020 | Not reported | 30 Jun 2025 | 31 Dec 2026 | +18 months |
| Emerald BayP52100026020 | Mundhawa | 2020 | Not reported | 30 Jun 2025 | 31 Dec 2026 | +18 months |
| Emerald BayP52100026022 | Mundhawa | 2020 | Not reported | 30 Jun 2025 | 31 Dec 2026 | +18 months |
| Emerald BayP52100026099 | Mundhawa | 2020 | Not reported | 30 Jun 2028 | 31 Dec 2029 | +18 months |
| Emerald BayP52100026110 | Mundhawa | 2020 | Not reported | 30 Jun 2025 | 31 Dec 2029 | +54 months |
| Emerald BayP52100026132 | Mundhawa | 2020 | Not reported | 30 Jun 2031 | — | On date |
| Purva AtmosphereP52100078943 | Keshavnagarmundwa | 2025 | Not reported | 31 Dec 2030 | — | On date |
| Purva AtmosphereP52100078951 | Keshavnagarmundwa | 2025 | Not reported | 31 Dec 2030 | — | On date |
| Purva AtmosphereP52100079121 | Keshavnagarmundwa | 2025 | Not reported | 31 Dec 2030 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 54 months, for Emerald Bay (P52100026110).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME:EMERALD BAY BUILDING 3 (Regulatory Case No. 266 OF 2024) dated 2 Aug 2024. · Emerald Bay · P52100026016 · 2 Aug 2024
- Regulatory orderRegulatory order: PROJECT NAME:EMERALD BAY BUILDING 3 (Regulatory Case No. 266 OF 2024) dated 2 Aug 2024. · Emerald Bay · P52100026020 · 2 Aug 2024
- Regulatory orderRegulatory order: PROJECT NAME:EMERALD BAY BUILDING 3 (Regulatory Case No. 266 OF 2024) dated 2 Aug 2024. · Emerald Bay · P52100026022 · 2 Aug 2024
- Regulatory orderRegulatory order: PROJECT NAME: LAWNS AND BEYOND - PHASE 1, OMKAR INTERNATIONAL DISTRICT (Regulatory Case No. 275 OF 2024) dated 02 Aug 2024. · Emerald Bay · P52100026020 · 31 Jul 2024
- Regulatory orderRegulatory order: PROJECT NAME: LAWNS AND BEYOND - PHASE 2, OMKAR INTERNATIONAL DISTRICT (Regulatory Case No. 274 OF 2024) dated 31 July 2024. · Emerald Bay · P52100026020 · 31 Jul 2024
- Regulatory orderRegulatory order: PROJECT NAME:EMERALD BAY BUILDING 13 (Regulatory Case No. 270 OF 2024) dated 31 July 2024. · Emerald Bay · P52100026099 · 31 Jul 2024
- Regulatory orderRegulatory order: PROJECT NAME:EMERALD BAY BUILDING 13 (Regulatory Case No. 270 OF 2024) dated 31 July 2024. · Emerald Bay · P52100026110 · 31 Jul 2024
- Regulatory orderRegulatory order: PROJECT NAME:EMERALD BAY BUILDING 13 (Regulatory Case No. 270 OF 2024) dated 31 July 2024. · Emerald Bay · P52100026132 · 31 Jul 2024
- Regulatory orderRegulatory order: PROJECT NAME:EMERALD BAY BUILDING 11 (Regulatory Case No. 267 OF 2024) dated 31 July 2024. · Emerald Bay · P52100026016 · 31 Jul 2024
- Regulatory orderRegulatory order: PROJECT NAME:EMERALD BAY BUILDING 11 (Regulatory Case No. 267 OF 2024) dated 31 July 2024. · Emerald Bay · P52100026022 · 31 Jul 2024
- Regulatory orderRegulatory order: PROJECT NAME:EMERALD BAY BUILDING 11 (Regulatory Case No. 267 OF 2024) dated 31 July 2024. · Emerald Bay · P52100026020 · 31 Jul 2024
- Regulatory orderRegulatory order: PROJECT NAME:EMERALD BAY BUILDING 2 (Regulatory Case No. 265 OF 2024) dated 31 July 2024. · Emerald Bay · P52100026016 · 31 Jul 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology