Skip to content
Deedo home
Menu

Pune Projects Llp

Company or firm · 2 projects · 9 MahaRERA registrations

Projects29 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 4 past their proposed date, not extended
Median delay+18 movs RERA proposed date · 5 extended
Regulatory cases6MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Emerald BayP52100026016Mundhawa2020Not reported30 Jun 202531 Dec 2026+18 months
Emerald BayP52100026020Mundhawa2020Not reported30 Jun 202531 Dec 2026+18 months
Emerald BayP52100026022Mundhawa2020Not reported30 Jun 202531 Dec 2026+18 months
Emerald BayP52100026099Mundhawa2020Not reported30 Jun 202831 Dec 2029+18 months
Emerald BayP52100026110Mundhawa2020Not reported30 Jun 202531 Dec 2029+54 months
Emerald BayP52100026132Mundhawa2020Not reported30 Jun 2031—On date
Purva AtmosphereP52100078943Keshavnagarmundwa2025Not reported31 Dec 2030—On date
Purva AtmosphereP52100078951Keshavnagarmundwa2025Not reported31 Dec 2030—On date
Purva AtmosphereP52100079121Keshavnagarmundwa2025Not reported31 Dec 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Emerald Bay+18 mo
  • Emerald Bay+18 mo
  • Emerald Bay+18 mo
  • Emerald Bay+18 mo
  • Emerald Bay+54 mo
  • Emerald BayOn date
  • Purva AtmosphereOn date
  • Purva AtmosphereOn date
  • Purva AtmosphereOn date

Track record notes

  • 0 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 54 months, for Emerald Bay (P52100026110).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology