Emerald Bay
Completion due Jun 2031Mundhawa, Pune 411036 |Promoter: Pune Projects LLP
Project summary
As registered with MahaRERA
- RERA registrations
- 6
- Phases
- 6
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year and 6 months
P52100026016- Registered
- 9 Aug 2020
- Promised
- 30 Jun 2025
- Revised
- 31 Dec 2026
Completion pushed back 1 year and 6 months
P52100026022- Registered
- 9 Aug 2020
- Promised
- 30 Jun 2025
- Revised
- 31 Dec 2026
Completion pushed back 1 year and 6 months
P52100026020- Registered
- 9 Aug 2020
- Promised
- 30 Jun 2025
- Revised
- 31 Dec 2026
Completion pushed back 4 years and 6 months
P52100026110- Registered
- 19 Aug 2020
- Promised
- 30 Jun 2025
- Revised
- 31 Dec 2029
Show 2 more registrations
Completion pushed back 1 year and 6 months
P52100026099- Registered
- 19 Aug 2020
- Promised
- 30 Jun 2028
- Revised
- 31 Dec 2029
Completion promised for 30 Jun 2031
P52100026132- Registered
- 21 Aug 2020
- Promised
- 30 Jun 2031
6 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100026016 | 9 Aug 2020 | 30 Jun 2025 | 31 Dec 2026 | Pune Projects LLP | Project page |
| P52100026022 | 9 Aug 2020 | 30 Jun 2025 | 31 Dec 2026 | Pune Projects LLP | Project page |
| P52100026020 | 9 Aug 2020 | 30 Jun 2025 | 31 Dec 2026 | Pune Projects LLP | Project page |
| P52100026110 | 19 Aug 2020 | 30 Jun 2025 | 31 Dec 2029 | Pune Projects LLP | Project page |
| P52100026099 | 19 Aug 2020 | 30 Jun 2028 | 31 Dec 2029 | Pune Projects LLP | Project page |
| P52100026132 | 21 Aug 2020 | 30 Jun 2031 | — | Pune Projects LLP | Project page |
Documents
11 documents held by Deedo
Registration certificates
- Registration certificateP52100026016 · 8 Sep 2021ViewSource
- Registration certificateP52100026022 · 8 Sep 2021ViewSource
- Registration certificateP52100026020 · 8 Sep 2021ViewSource
- Registration certificateP52100026110 · 8 Sep 2021ViewSource
- Registration certificateP52100026099 · 8 Sep 2021ViewSource
- Registration certificateP52100026132 · 21 Aug 2026ViewSource
Extension certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- Regulatory order2 Aug 2024Matched by RERA number
Regulatory order: PROJECT NAME:EMERALD BAY BUILDING 3 (Regulatory Case No. 266 OF 2024) dated 2 Aug 2024.
- Regulatory order31 Jul 2024Matched by RERA number
Regulatory order: PROJECT NAME: LAWNS AND BEYOND - PHASE 1, OMKAR INTERNATIONAL DISTRICT (Regulatory Case No. 275 OF 2024) dated 02 Aug 2024.
- Regulatory order31 Jul 2024Matched by RERA number
Regulatory order: PROJECT NAME: LAWNS AND BEYOND - PHASE 2, OMKAR INTERNATIONAL DISTRICT (Regulatory Case No. 274 OF 2024) dated 31 July 2024.
- Regulatory order31 Jul 2024Matched by RERA number
Regulatory order: PROJECT NAME:EMERALD BAY BUILDING 13 (Regulatory Case No. 270 OF 2024) dated 31 July 2024.
- Regulatory order31 Jul 2024Matched by RERA number
Regulatory order: PROJECT NAME:EMERALD BAY BUILDING 11 (Regulatory Case No. 267 OF 2024) dated 31 July 2024.
- Regulatory order31 Jul 2024Matched by RERA number
Regulatory order: PROJECT NAME:EMERALD BAY BUILDING 2 (Regulatory Case No. 265 OF 2024) dated 31 July 2024.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Mundhawa
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.