Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100023397

Shri Samarth · Shukrawar Peth, Pune · Samarth Construction

Promised for 1 Dec 2022, extended once to 30 Nov 2023 — and that date has passed without the project marked complete on MahaRERA.

3 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 1 Dec 2022 to 30 Nov 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Nov 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate12 Dec 2019View
Extension certificate30 Jan 2023View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100023397

Is Shri Samarth delayed?

Yes. MahaRERA records a promised completion of 1 Dec 2022, revised to 30 Nov 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100023397. The completion date moved from 1 Dec 2022 to 30 Nov 2023.

Who is the promoter?

MahaRERA records Samarth Construction as the promoter of P52100023397.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100023397.

Answers are generated from the record.

Data through3 Nov 2026, 02:01SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology