RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100022592
Shreejis Orion · Somatane, Pune · Vn Developers
Promised for 28 Aug 2022, extended once to 31 May 2026 — and that date has passed without the project marked complete on MahaRERA.
4 years and 3 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 28 Aug 2022 to 31 May 2026 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 May 2026, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 3
Orders 0
No MahaRERA order or list names this number.
Questions about P52100022592
Is Shreejis Orion delayed?
Yes. MahaRERA records a promised completion of 28 Aug 2022, revised to 31 May 2026, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100022592. The completion date moved from 28 Aug 2022 to 31 May 2026.
Who is the promoter?
MahaRERA records Vn Developers as the promoter of P52100022592.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100022592.
Answers are generated from the record.
