Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100021496

La Ventana Phase 2 · Kondhwa Khurd, Pune · Laventana Llp

Promised for 30 Dec 2022, extended once to 30 Apr 2023 — and that date has passed without the project marked complete on MahaRERA.

3 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2022 to 30 Apr 2023 (1 extension certificate on record).
  • Caution: The latest completion date on record, 30 Apr 2023, has passed.

Documents 2

Registration certificate16 Feb 2024View
Extension certificate16 Feb 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100021496

Is La Ventana Phase 2 delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2022, revised to 30 Apr 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100021496. The completion date moved from 30 Dec 2022 to 30 Apr 2023.

Who is the promoter?

MahaRERA records Laventana Llp as the promoter of P52100021496.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100021496.

Answers are generated from the record.

Data through24 Oct 2026, 02:15SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology