Laventana Llp

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Laventana Phase IP52100009383Pune (M Corp.)2017Certificate Signed30 Mar 202230 Mar 2022On date
La Ventana Phase 2P52100021496Kondhwa Khurd2019Certificate Signed30 Dec 202230 Apr 2023+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Laventana Phase IOn date
  • La Ventana Phase 2+4 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for La Ventana Phase 2 (P52100021496).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology