Registered1 extensionMahaRERA status: Certificate Signed

P52100016663

Atlante · Tathwade, Pune · Pyramid Infraventure Llp

Promised for 30 Dec 2025, extended once to 30 Dec 2027, which is still ahead.

The revised date is 2 years after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2025 to 30 Dec 2027 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Extension certificate16 Jun 2025View
Registration certificate23 Jun 2025View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100016663

Is Atlante delayed?

Its completion moved from 30 Dec 2025 to 30 Dec 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100016663. The completion date moved from 30 Dec 2025 to 30 Dec 2027.

Who is the promoter?

MahaRERA records Pyramid Infraventure Llp as the promoter of P52100016663.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100016663.

Answers are generated from the record.

Data through9 Nov 2026, 01:59SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology