Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered1 extensionMahaRERA status: Certificate Signed

P52100015755

Vision One Phase Two · Tathwade, Pune · Ss Group

Promised for 28 May 2021, extended once to 31 Dec 2026, which is still ahead.

The revised date is 5 years and 7 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 28 May 2021 to 31 Dec 2026 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate21 Jun 2024View
Extension certificate1 Jan 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100015755

Is Vision One Phase Two delayed?

Its completion moved from 28 May 2021 to 31 Dec 2026; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100015755. The completion date moved from 28 May 2021 to 31 Dec 2026.

Who is the promoter?

MahaRERA records Ss Group as the promoter of P52100015755.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100015755.

Answers are generated from the record.

Data through9 Nov 2026, 01:59SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology