Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100015576

Shalini Shubharambh · Ambegaon Kh, Pune · Shalini Developers

Promised for 31 Dec 2019, extended once to 30 Jun 2022 — and that date has passed without the project marked complete on MahaRERA.

6 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2019 to 30 Jun 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate8 Mar 2018View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100015576

Is Shalini Shubharambh delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2019, revised to 30 Jun 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100015576. The completion date moved from 31 Dec 2019 to 30 Jun 2022.

Who is the promoter?

MahaRERA records Shalini Developers as the promoter of P52100015576.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100015576.

Answers are generated from the record.

Data through9 Nov 2026, 01:59SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology