Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100015575

Creative Orchid · Punawale, Pune · Creative Infra Tech

Promised for 30 Dec 2021, extended once to 30 Jun 2024 — and that date has passed without the project marked complete on MahaRERA.

4 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2021 to 30 Jun 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate9 Sep 2021View
Extension certificate9 May 2023View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100015575

Is Creative Orchid delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2021, revised to 30 Jun 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100015575. The completion date moved from 30 Dec 2021 to 30 Jun 2024.

Who is the promoter?

MahaRERA records Creative Infra Tech as the promoter of P52100015575.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100015575.

Answers are generated from the record.

Data through9 Nov 2026, 01:52SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology