P52100015506
Dev Residency Phase 1 · Uruli Devachi, Pune · Shraddha Construction
Promised for 30 Nov 2018, extended once to 30 Nov 2019 — and that date has passed without the project marked complete on MahaRERA.
8 years past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Nov 2018 to 30 Nov 2019 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Nov 2019, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100015506
Is Dev Residency Phase 1 delayed?
Yes. MahaRERA records a promised completion of 30 Nov 2018, revised to 30 Nov 2019, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100015506. The completion date moved from 30 Nov 2018 to 30 Nov 2019.
Who is the promoter?
MahaRERA records Shraddha Construction as the promoter of P52100015506.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100015506.