Rudra Samruddhi · Uruli Kanchan, Pune · Shivrudra Constructions
Promised for 1 Feb 2019, extended once to 31 Dec 2027, which is still ahead.
The revised date is 8 years and 10 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 1 Feb 2019 to 31 Dec 2027 (1 extension certificate on record).
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 20
Orders 0
No MahaRERA order or list names this number.
Questions about P52100015465
Is Rudra Samruddhi delayed?
Its completion moved from 1 Feb 2019 to 31 Dec 2027; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100015465. The completion date moved from 1 Feb 2019 to 31 Dec 2027.
Who is the promoter?
MahaRERA records Shivrudra Constructions as the promoter of P52100015465.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100015465.
Answers are generated from the record.