Shravan Corner · Pimpri Chinchawad (M Corp.), Pune · Suraj Buildcon

Promised for 31 Oct 2018, extended once to 31 Jul 2024 — and that date has passed without the project marked complete on MahaRERA.

8 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Oct 2018 to 31 Jul 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Jul 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate16 Oct 2017View
Extension certificate2 Aug 2023View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100013651

Is Shravan Corner delayed?

Yes. MahaRERA records a promised completion of 31 Oct 2018, revised to 31 Jul 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100013651. The completion date moved from 31 Oct 2018 to 31 Jul 2024.

Who is the promoter?

MahaRERA records Suraj Buildcon as the promoter of P52100013651.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100013651.