RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100012957

Sadguru Complex · Dehu, Pune · Jare Buildcon Pvt Ltd

Promised for 31 Dec 2019, extended once to 30 May 2025 — and that date has passed without the project marked complete on MahaRERA.

6 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2019 to 30 May 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 May 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate7 Sep 2017View
Extension certificate7 Feb 2022View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100012957

Is Sadguru Complex delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2019, revised to 30 May 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100012957. The completion date moved from 31 Dec 2019 to 30 May 2025.

Who is the promoter?

MahaRERA records Jare Buildcon Pvt Ltd as the promoter of P52100012957.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100012957.

Answers are generated from the record.

Data through1 Nov 2026, 02:02SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology