P52100012495

Vishwa Kunj Phase 1 · Bopodi, Pune · Archway Realltors

Promised for 30 Mar 2019 — that date has passed and MahaRERA does not mark the project complete.

7 years and 8 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Deedo holds 1 extension certificate for this registration.
  • Risk: The latest completion date on record, 30 Mar 2019, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate1 Sep 2017View
Extension certificate3 May 2018View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100012495

Is Vishwa Kunj Phase 1 delayed?

Yes. MahaRERA records a promised completion of 30 Mar 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100012495.

Who is the promoter?

MahaRERA records Archway Realltors as the promoter of P52100012495.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100012495.

Answers are generated from the record.

Data through9 Nov 2026, 02:51SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology