Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52100010724

Shri Balaji Utsav · Pune (M Corp.), Pune · Shri Balaji Housing Co

Promised for 1 Mar 2021 — that date has passed and MahaRERA does not mark the project complete.

5 years and 8 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 1 Mar 2021, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate18 May 2020View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100010724

Is Shri Balaji Utsav delayed?

Yes. MahaRERA records a promised completion of 1 Mar 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100010724.

Who is the promoter?

MahaRERA records Shri Balaji Housing Co as the promoter of P52100010724.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100010724.