P52100010450
Krupasindhu Shailya · Kadamwak Wasti, Pune · Dhanlaxmi Builders And Developers
Promised for 1 May 2019, extended once to 30 Oct 2020 — and that date has passed without the project marked complete on MahaRERA.
7 years and 6 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 1 May 2019 to 30 Oct 2020 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Oct 2020, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100010450
Is Krupasindhu Shailya delayed?
Yes. MahaRERA records a promised completion of 1 May 2019, revised to 30 Oct 2020, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100010450. The completion date moved from 1 May 2019 to 30 Oct 2020.
Who is the promoter?
MahaRERA records Dhanlaxmi Builders And Developers as the promoter of P52100010450.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100010450.