Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52100009389

Constructing 54 Tenements LIG and 36 Tenements MIG at Gat No 1712 part Dive Taluka Purander Dist Pun · Dive, Pune · Pune Hsg. & Area Devp. Board

Promised for 30 Jun 2018 — that date has passed and MahaRERA does not mark the project complete.

8 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Jun 2018, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate22 Aug 2017View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100009389

Is Constructing 54 Tenements LIG and 36 Tenements MIG at Gat No 1712 part Dive Taluka Purander Dist Pun delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100009389.

Who is the promoter?

MahaRERA records Pune Hsg. & Area Devp. Board as the promoter of P52100009389.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100009389.

Answers are generated from the record.

Data through31 Oct 2026, 01:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology