P52100008065

Platinum Park · Man, Pune · Saffron Properties And Schemes

Promised for 30 Jun 2021, extended once to 31 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

5 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2021 to 31 Dec 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate18 Aug 2017View
Extension certificate21 Jun 2024View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100008065

Is Platinum Park delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2021, revised to 31 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100008065. The completion date moved from 30 Jun 2021 to 31 Dec 2024.

Who is the promoter?

MahaRERA records Saffron Properties And Schemes as the promoter of P52100008065.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100008065.

Answers are generated from the record.