Registered1 extensionMahaRERA status: Certificate Signed

P52100007982

Sukhwani Gracia · Sus, Pune · Prime Properties

Promised for 10 Apr 2021, extended once to 31 Dec 2027, which is still ahead.

The revised date is 6 years and 8 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 10 Apr 2021 to 31 Dec 2027 (1 extension certificate on record).
  • Caution: 1 other MahaRERA order names this registration.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 Aug 2017View
Extension certificate13 Jan 2026View

Orders 1

Regulatory order

Regulatory order: PROJECT NAME:Sukhwani Gracia Phase-3 C, Wing (Regulatory Case No. 167 of 2024) dated 13 March 2024.

13 Mar 2024 · matched by RERA number

View order →

Questions about P52100007982

Is Sukhwani Gracia delayed?

Its completion moved from 10 Apr 2021 to 31 Dec 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100007982. The completion date moved from 10 Apr 2021 to 31 Dec 2027.

Who is the promoter?

MahaRERA records Prime Properties as the promoter of P52100007982.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P52100007982.

Answers are generated from the record.

Data through28 Oct 2026, 01:43SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology