Company or firm · first RERA registration 2017
Prime Properties
Deedo IDDD-2S65Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 80 mo late — longer than Maharashtra's 4 mo.
Projects12 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay80 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Sukhwani GraciaRegulatory order: PROJECT NAME:Sukhwani Gracia Phase-3 C, Wing (Regulatory Case No. 167 of 2024) dated 13 March 2024. | 13 Mar 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sukhwani GraciaP52100007297 | Sus | Certificate Signed | 10 Apr 2019 | 10 Apr 2019 | On date |
| Sukhwani GraciaP52100007982 | Sus | Certificate Signed | 10 Apr 2021 | 31 Dec 2027 | +80 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology