Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100007354

Navi Tulsibaug · Pune (M Corp.), Pune · Matoshri Estate Pvt Ltd

Promised for 30 Dec 2023, extended once to 25 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.

2 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2023 to 25 Dec 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 25 Dec 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate10 Jan 2023View
Extension certificate10 Mar 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100007354

Is Navi Tulsibaug delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2023, revised to 25 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100007354. The completion date moved from 30 Dec 2023 to 25 Dec 2025.

Who is the promoter?

MahaRERA records Matoshri Estate Pvt Ltd as the promoter of P52100007354.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100007354.

Answers are generated from the record.

Data through9 Nov 2026, 01:48SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology