RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100006791
Impulse Residency · Lohgaon, Pune · Impulse Buildcon
Promised for 31 May 2018, extended once to 30 Jun 2024 — and that date has passed without the project marked complete on MahaRERA.
8 years and 5 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 May 2018 to 30 Jun 2024 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Jun 2024, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 3
Orders 0
No MahaRERA order or list names this number.
Questions about P52100006791
Is Impulse Residency delayed?
Yes. MahaRERA records a promised completion of 31 May 2018, revised to 30 Jun 2024, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100006791. The completion date moved from 31 May 2018 to 30 Jun 2024.
Who is the promoter?
MahaRERA records Impulse Buildcon as the promoter of P52100006791.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100006791.
Answers are generated from the record.
