Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100006200
Kool Homes Galaxy · Erandwana, Pune · Ethix Vandan
Promised for 31 Dec 2019, extended once to 31 Dec 2022 — and that date has passed without the project marked complete on MahaRERA.
6 years and 11 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2019 to 31 Dec 2022 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Dec 2022, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 3
Orders 0
No MahaRERA order or list names this number.
Questions about P52100006200
Is Kool Homes Galaxy delayed?
Yes. MahaRERA records a promised completion of 31 Dec 2019, revised to 31 Dec 2022, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100006200. The completion date moved from 31 Dec 2019 to 31 Dec 2022.
Who is the promoter?
MahaRERA records Ethix Vandan as the promoter of P52100006200.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100006200.
Answers are generated from the record.