RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100006145
Auroville · Jalochi, Pune · Ashapurabuildcon Builder And Developers
Promised for 31 Dec 2017 — that date has passed and MahaRERA does not mark the project complete.
8 years and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Risk: The latest completion date on record, 31 Dec 2017, has passed.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P52100006145
Is Auroville delayed?
Yes. MahaRERA records a promised completion of 31 Dec 2017, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 0 extension certificates for P52100006145.
Who is the promoter?
MahaRERA records Ashapurabuildcon Builder And Developers as the promoter of P52100006145.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100006145.
Answers are generated from the record.