Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52100005625

Arjun Residency 5th Floor · Pune (M Corp.), Pune · S M Beharay And Company

Promised for 31 Dec 2017 — that date has passed and MahaRERA does not mark the project complete.

8 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2017, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate11 Aug 2017View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100005625

Is Arjun Residency 5th Floor delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2017, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100005625.

Who is the promoter?

MahaRERA records S M Beharay And Company as the promoter of P52100005625.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100005625.

Answers are generated from the record.

Data through16 Nov 2026, 01:41SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology