RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52100005400

Mango One B-C · Hadapsar, Pune · Mango Lifestyle Private Limited

Promised for 31 Dec 2017 — that date has passed and MahaRERA does not mark the project complete.

8 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2017, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate11 Aug 2017View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100005400

Is Mango One B-C delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2017, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100005400.

Who is the promoter?

MahaRERA records Mango Lifestyle Private Limited as the promoter of P52100005400.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100005400.

Answers are generated from the record.