Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passed1 extensionMahaRERA status: Certificate Signed

P52100003209

Kutumb Prime · Mawal, Pune · Naiknavare Buildcon Pvt Ltd

Promised for 29 Jun 2023 — that date has passed and MahaRERA does not mark the project complete.

3 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Deedo holds 1 extension certificate for this registration.
  • Risk: The latest completion date on record, 29 Jun 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate13 Oct 2022View
Extension certificate13 Oct 2022View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100003209

Is Kutumb Prime delayed?

Yes. MahaRERA records a promised completion of 29 Jun 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100003209.

Who is the promoter?

MahaRERA records Naiknavare Buildcon Pvt Ltd as the promoter of P52100003209.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100003209.

Answers are generated from the record.

Data through3 Nov 2026, 01:39SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology