Mohar Pratima · Talegaon Dabhade (M Cl), Pune · Mohar Housing Llp
Promised for 30 Jun 2021, extended once to 30 Jun 2025 — and that date has passed without the project marked complete on MahaRERA.
5 years and 5 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2021 to 30 Jun 2025 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Jun 2025, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 3
Orders 0
No MahaRERA order or list names this number.
Questions about P52100001910
Is Mohar Pratima delayed?
Yes. MahaRERA records a promised completion of 30 Jun 2021, revised to 30 Jun 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100001910. The completion date moved from 30 Jun 2021 to 30 Jun 2025.
Who is the promoter?
MahaRERA records Mohar Housing Llp as the promoter of P52100001910.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100001910.
Answers are generated from the record.