RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100001274

Park Titanium Phase II · Wakad, Pune · Pride Purple Properties

Promised for 30 Oct 2022, extended once to 29 Oct 2023 — and that date has passed without the project marked complete on MahaRERA.

4 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Oct 2022 to 29 Oct 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 29 Oct 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
Extension certificate20 Oct 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100001274

Is Park Titanium Phase II delayed?

Yes. MahaRERA records a promised completion of 30 Oct 2022, revised to 29 Oct 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100001274. The completion date moved from 30 Oct 2022 to 29 Oct 2023.

Who is the promoter?

MahaRERA records Pride Purple Properties as the promoter of P52100001274.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100001274.

Answers are generated from the record.

Data through16 Nov 2026, 01:38SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology