Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100000805

Skyi Songbirds Phase C · Bhugaon, Pune · Enerrgia Skyi Developers

Promised for 30 Nov 2020, extended once to 31 Dec 2023 — and that date has passed without the project marked complete on MahaRERA.

5 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Nov 2020 to 31 Dec 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 May 2020View
Extension certificate25 May 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100000805

Is Skyi Songbirds Phase C delayed?

Yes. MahaRERA records a promised completion of 30 Nov 2020, revised to 31 Dec 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100000805. The completion date moved from 30 Nov 2020 to 31 Dec 2023.

Who is the promoter?

MahaRERA records Enerrgia Skyi Developers as the promoter of P52100000805.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100000805.

Answers are generated from the record.

Data through25 Oct 2026, 01:47SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology