Enerrgia Skyi Developers
Company or firm · 8 projects · 8 MahaRERA registrations
8Projects8 RERA registrations
0Completedas reported on MahaRERA project pages
38%Kept RERA date3 of 8 past their proposed date, not extended
+18 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Skyi Songbirds Phase DP52100000764 | Bhugaon | 2017 | Certificate Signed | 30 Nov 2020 | 30 May 2022 | +18 months |
| Skyi Songbirds Phase AP52100000769 | Bhugaon | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Skyi Songbirds Phase CP52100000805 | Bhugaon | 2017 | Certificate Signed | 30 Nov 2020 | 31 Dec 2023 | +37 months |
| Skyi Songbirds Phase BP52100001117 | Bhugaon | 2017 | Certificate Signed | 30 Nov 2020 | 30 May 2022 | +18 months |
| Skyi Songbirds Phase EP52100019348 | Bhugaon | 2019 | Certificate Signed | 30 Jun 2024 | 31 Dec 2027 | +42 months |
| Skyi Songbirds CommercialP52100019378 | Bhugaon | 2019 | Certificate Signed | 28 Feb 2021 | 28 Aug 2022 | +18 months |
| Skyi Aria Heights Phase IP52100028121 | Bhugaon | 2021 | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | On date |
| Skyi Sula Heights Phase IIP52100029933 | Bhugaon | 2021 | Certificate Signed | 31 Jul 2025 | 31 Jul 2025 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 8 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 42 months, for Skyi Songbirds Phase E (P52100019348).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology