P52100000764

Skyi Songbirds Phase D · Bhugaon, Pune · Enerrgia Skyi Developers

Promised for 30 Nov 2020, extended once to 30 May 2022 — and that date has passed without the project marked complete on MahaRERA.

5 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Nov 2020 to 30 May 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 May 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 May 2020View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100000764

Is Skyi Songbirds Phase D delayed?

Yes. MahaRERA records a promised completion of 30 Nov 2020, revised to 30 May 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100000764. The completion date moved from 30 Nov 2020 to 30 May 2022.

Who is the promoter?

MahaRERA records Enerrgia Skyi Developers as the promoter of P52100000764.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100000764.

Answers are generated from the record.

Data through25 Oct 2026, 01:47SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology